top of page
EAFUF04.png

Сhernihiv Regional Children’s Hospital

Equipment for setting up a solar station was received
The official opening day of the hybrid solar station at the Chernihiv Regional Children's Hospital.

April 3

May 10

February

April 11-24

The project at the Chernihiv Oblast Children's Hospital started. 
Installation of the solar panels on the roof
The official opening day of the hybrid solar station at the Chernihiv Regional Children's Hospital. 
May 10

 

98 panels with a capacity of 44.59 kW, equipped with ZCS Azzurro inverters and energy storage systems totalling 96 kWh were equipped on the roof.  This system will cover 99.8% of the consumption of the neonatal intensive care unit for premature infants. It will also cover the consumption of the neonatal intensive care unit for premature infants for up to 8 hours in case of outages.  

Сonstruction and installation works
April 11-24

construction and installation works at the Chernihiv Regional Children's Hospital. Installation of the solar panels on the roof. 

April 3

equipment for setting up a solar station at the Chernihiv Oblast Children's Hospital was received, namely:  

  

  • 98 panels with a capacity of 44.59 kW  

  • ZCS Azzurro inverters  

  • energy storage systems totalling 96 kWh  

February

the project at the Chernihiv Oblast Children's Hospital started.  

Partners and donors:

Menlo.png
unisolar.png

Project cost:
approx.
93 400 EUR

Campaigns in numbers

Сhernihiv Regional Children’s Hospital.png
bottom of page