Сhernihiv School № 19

We received equipment from our partners

November

The official launch of the solar station

December 22

November 21

Installation of the solar panels

A solar plant with energy storage systems was put into operation at Chernihiv Secondary School 19

The official launch of the solar station

December 22

 

A solar station with electricity storage systems with a total capacity of 20 kW was installed on the school's roof. These systems provide an independent power supply for the school for up to 4 hours when the primary source of electricity is turned off. From now on, 20% of the school's annual energy consumption will be provided by solar energy.

Installation of solar panels

November 21

 

​️Technical information about the object:

  • The power of the station is 20 kW

  • The capacity of battery units is 39.2 kWh

We received equipment from our partners.

November

Ukrainian World Congress and Energize Ukraine provided financial donations for the project implementation. 

Menlo Electric provided solar panels.

FoxEss Polska provided inverters and energy storage.

In November, we received equipment from our partners, Menlo Electric and FoxEssPolska.

  • Photoelectric modules Jinko 455 — 57 pcs

  • Inverter equipment — 2 pc

  • Lithium-iron-phosphate batteries — 16 pcs.

Donors: Menlo Electric S.A., Ukrainian World Congress, FoxEss Polska

Technical partner: Rodina

The total budget of the project:  29 827 EUR